Defining your need and your specification

Asking the right questions before rushing in

Defining your need and your specification

Understand why a clear specification saves you from heading off in all directions mid-project, and how to write a simple and useful one.

Documentation completed: 70% 70
Created by:  Adrien Bracq

The “we’ll see as we go” trap

On a project, the urge to start soldering, printing or coding is strong: it is often why people sign up to the MakerSpace. But starting without having set out the need is the best way to make the same choices three times over, to discover a blocking constraint in week 6, or to deliver a prototype that no longer answers the original question at all.

  Warning

A specification is not an administrative exercise to be done for form’s sake. It is the tool that saves you from losing weeks starting over.

A specification does not need to be long or formal. It just has to answer five questions clearly, before the first line of code or the first printed part.

The five questions to ask yourself

Ask yourself these questions in this order; it is the natural line of reasoning: why → what → for whom → within what limits → how we check. They are exactly the five sections of the template further down, in the same order: what you answer here, you copy into it as it is.

  • Context: why does this project exist? What problem was observed, what opportunity?
  • Objectives: what must the project achieve in concrete terms, stated in a verifiable way (not wishful thinking)?
  • Target audience: who will use or see this project? A jury, visitors to the Forum des Sciences, a future year group that will pick up the work?
  • Constraints: time available, budget, equipment accessible at the MakerSpace, the team’s real skills (not those you hope to acquire along the way).
  • Success criteria: how will you know, at the end, that the project has reached its objective? If the answer is fuzzy, so is the objective.

Vague objective vs precise objective: an example

The “Objectives” section is the one most often lacking: the difference between a poorly scoped objective and a well scoped one shows immediately when you read it.

Objective: “Make a robot that sorts waste.”

What is missing: what volume of waste, which categories, what budget, what deadline, what level of reliability is expected. With this statement, the team cannot know whether it has finished, or whether it is still on track halfway through.

Objective: “Design a robot able to sort 3 categories of waste (plastic, glass, metal) placed on a 1 m conveyor belt, for a demonstration at the Forum des Sciences on 15 May. Maximum budget €150, time frame of 8 weeks, target rate of correct sorting: 80% minimum over 20 trials.”

What this allows: the team can share out the work, know whether a technical choice fits the budget, and check objectively at the end whether the objective has been reached.

A simple template to reuse

You do not need to invent a format. This template fits in the docs/objectifs.md page of your repo, which organises it in three sections: Contexte (context), Problème et public cible (problem and target audience: the “Objectives” and “Target audience” headings below), and Cahier des charges (specification: the “Constraints” and “Success criteria” headings, in the form of a table of functions, see below). Fill it in as a team at the very first project meeting.

## Context

<Why this project exists. What problem was observed, what opportunity.>

## Objectives

<What the project must achieve, stated in a verifiable way.>

## Target audience

<Who uses or assesses the result.>

## Constraints

- Time frame:
- Budget:
- Equipment / machines available:
- Skills of the team:

## Success criteria

<How we know, objectively, that it is a success.>
  Good practice

Fill in this template together, out loud, at the very first meeting, not one team member alone in a corner. It is also the moment when disagreements about what the project must do come out, and it is better for that to happen on day 1 than on day 40.

Filled-in example

Here is what the template looks like once filled in, for the sorting robot project used as an example on this page:

## Context

The Forum des Sciences in Amiens wants an educational activity about
waste sorting for its May edition. There is currently no mechanical
sorting demonstration in the programme.

## Objectives

Design a robot able to sort 3 categories of waste (plastic,
glass, metal) placed on a 1 m conveyor belt, for a public
demonstration on 15 May.

## Target audience

The visitors (families, school groups) and the activity team of the Forum des
Sciences, who must be able to run the robot without us being there
on the day.

## Constraints

- Time frame: 8 weeks
- Budget: €150 maximum
- Equipment / machines available: 3D printer, laser cutter, Arduino
- Skills of the team: basic electronics, no experience in
  camera vision

## Success criteria

Rate of correct sorting ≥ 80% over 20 trials, robot running without
technical supervision during the demonstration, total cost ≤ €150.

Notice that “Context” and “Objectives” do not say the same thing: the first explains why the project exists, the second says what has to be delivered. If you do not know what to write in “Objectives”, reread your “Context”: the objective is often the direct answer to the problem raised.

To fill in the “Objectives” and “Success criteria” sections without staying at the level of vague intentions, there are a few structured methods. They are detailed just below. They are not only for filling in a document: they produce a concrete aid that you will reuse later in the project to compare and justify real technical choices.

Going further: the functional specification

The template above is enough for the vast majority of MakerSpace projects. If your project is more ambitious, or if your academic supervisor expects a more formal engineering approach, functional analysis (standard NF EN 16271) gives three simple tools to firm up the need before designing.

  Do not turn it into a chore

These three tools are not mandatory and do not replace the previous template. They are sketches to do on the board in 15-20 minutes as a team, not an administrative file to produce for form’s sake. Use only what really helps you see clearly.

The “horned beast” diagram: stating the need in one sentence

This diagram (bête à cornes in French) forces you to answer three questions about the project, to arrive at a statement of the need in one clear sentence.

graph LR
    A[Whom does the project<br/>serve?] --> P((The sorting<br/>robot))
    C[For what purpose?] --> P
    P --> B[What does it act on?]

For the sorting robot example: “The sorting robot serves the visitors to the Forum des Sciences, by acting on mixed waste, for the purpose of demonstrating reliable automatic sorting.”

The octopus diagram: listing the functions to provide

It places the product at the centre and brings out the elements of its environment (users, other objects, physical constraints). Each link becomes a function to provide:

  • FP (fonction principale, main function): what the product must do
  • FC (fonction contrainte, constraint function): what it must adapt to
graph TD
    Produit((Sorting robot))
    Dechets[Mixed waste]
    Visiteur[Forum visitor]
    Alim[Power supply]
    Tapis[Existing conveyor belt]
    Budget[Budget €150]

    Produit ---|FP1: sort the waste| Dechets
    Produit ---|FP2: inform the visitor| Visiteur
    Produit ---|FC1: be powered| Alim
    Produit ---|FC2: fit onto the belt| Tapis
    Produit ---|FC3: keep to the budget| Budget

Each function listed here can then become a concrete success criterion in your template.

The table of functions: making each function measurable

For each function identified in the octopus diagram, you specify an assessment criterion (how it is measured), an expected level (the target value), and a flexibility (possible room for negotiation: F0 = imposed, non-negotiable; F1 = hardly negotiable; F2 = negotiable; F3 = a wish, not essential).

Function Assessment criterion Expected level Flexibility
FP1: sort the waste Rate of correct sorting ≥ 80% over 20 trials F1
FP2: inform the visitor Readability of the explanatory panel Readable at 2 m F2
FC1: be powered Type of power supply 220 V mains or battery ≥ 4 h F0
FC2: fit onto the belt Width compatible with the belt ≤ 1 m F0
FC3: keep to the budget Total cost of the project ≤ €150 F0
Copy the table (Markdown)
| Function | Assessment criterion | Expected level | Flexibility |
|---|---|---|---|
| FP1: ... | ... | ... | F0/F1/F2/F3 |
| FC1: ... | ... | ... | F0/F1/F2/F3 |

It is this table, more than the diagrams themselves, that becomes directly reusable: each row can be copied as it is into the “Success criteria” of the template seen above. It is also the table that the Cahier des charges section of docs/objectifs.md contains, with this same sorting robot example to be replaced by your functions.

The FAST diagram: moving from functions to solutions

FAST starts from a function (e.g. “sort the waste”) and breaks it down into technical sub-functions, down to the concrete solutions considered. We do not detail it here: it mostly belongs later in the project, when comparing and justifying technical choices. See Recording your technical choices.

This specification is not set in stone

A project evolves: an unforeseen hardware constraint, a component out of stock, an idea that turns out to be better along the way. The specification can change, but it must change consciously and in writing, not silently in one person’s head. Each revision is documented in the same place, with the date and the reason for the change.

This is the direct link with the rest of the workshop: this scoping document is the first piece of documentation that will live throughout the project, not only at the end.

Exercise

On your own project, as a team and out loud:

  1. Fill in the docs/objectifs.md page of your repo: the five headings of the template (Context, Objectives, Target audience, Constraints, Success criteria) fit in its three sections.
  2. Reread your “Success criteria”: can they be verified by someone outside the team, or only understood by you?
  3. If your project is ambitious or your supervisor asks for it, quickly draw a horned beast diagram and an octopus diagram in 15-20 minutes.